HNA Edinburgh
|
Contract Value
Client
Construction Period |
![]() |
The project's aim is to provide Adelaide based elements of 1st Brigade with facilities and supporting infrastructure ready for occupation from January 2011 in order to achieve the Government intent for the Hardened and Networked Army. The project will provide permanent working accommodation for a mechanised infantry battalion, artillery, engineer and combat services support subunits, plus infrastructure and replacement common user facilities to meet both army and RAAF requirements at EDP.
Civil Works
- Installation and commissioning of the stormwater drainage system
- Installation and commissioning of numerous downstream defenders
- Design, installation and commissioning of stormwater retention cell process plant
Hydraulic Works
- Design and construct of the site wide effluent collection system, including pump stations and control systems
- Installation and commissioning of the site wide sewerage system.
- Installation and commissioning of the potable water and non-potable water systems
- Installation of irrigation conduits for future irrigation systems
- Installation and commissioning of the fire main and fire service systems
Mechanical Works
- Installation and commissioning of the gas supply system, including meters and regulators
Jacinth Ambrosia Water Supply
|
Contract Value
Client
Construction Period |
![]() |
The remoteness and the environmental sensitivity of the area presented major challenges to the timely delivery of the project.
B J Jarrad Pty Ltd were involved in the design, development, and the delivery of the following multi disciplined works:
- Raw water GRP pipeline from the borefields to the process plant
- Down bore installation of bore pumps and associated civil works
- Fabrication and installation of stainless steel, carbon steel and poly pipe associated with the down bore pumps.
- Installation of fibre-optic cables for telemetry / control links
- Design and installation of the process water control system
- Major pump station and all associated mechanical and civil works including the fabrication and installation of stainless and carbon steel components
- Installation of lined storage dams including all civil works
- Potable water pipeline for the construction and the mining operations camp
- Design and installation of waste water treatment plant for the construction and operations camp
- Installation of 120 man camp and all associated services
- Installation and commissioning of RO plant for the provision of potable water for the entire project.
The project was delivered on time and on budget providing the client with process water within the agreed construction program.
Jacinth Ambrosia Appreciation Certificate


ASC Shipyards
B J Jarrad Pty Ltd were engaged to set out, excavate, install, test and commission all in-ground services including:
- Stormwater
- Gross Pollutant Traps
- Duraboom
- Sewer Mains & Sewer Pump Stations
- Potable and Non-Potable Water
- Industrial Gas Reticulation
- Fire Mains & Services
- Communication Cables
- High and Low Voltage Conduits
- Security Cables
One of the challenges of this project was the client's requirement to maintain the integrity of the pavement, which was rated at a point load of 40 tonne, above the services. Accurate trench excavation was a necessity where heavy duty pavement was required - for 80% of the project works. Due to unstable soil conditions at the site, concrete was used as the backfill material, so accuracy of laying was imperative.
Fire Tanks and a Fire Pump Room were designed, installed and commissioned to provide independent fire fighting facilities on site.
The design of the Gross Pollutant Traps and "off beach" Duraboom were innovative providing a challenge for the construction team, but these were constructed successfully.
All survey information was captured for the compilation of As Constructed drawings.
A very successful outcome was achieved by B J Jarrad Pty Ltd on one of the most high profile construction projects for South Australia in over twenty years.
Prominent Hill
|
Contract Value
Client
Construction Period |
![]() |
Between August 2006 and December 2008, B J Jarrad Pty Ltd completed several projects at Prominent Hill for the Prominent Hill Copper/Gold Mine. The site is approximately 110 kilometres south east of Coober Pedy.

B J Jarrad Pty Ltd constructed a 1200 person camp including installation of accommodation units, potable and non-potable water, and sewer infrastructure.
In addition to the initial contract scope of works, major variations were awarded which included earthworks, installation works on mess areas and ice rooms, construction of the airstrip lounge, concrete pathways and verandahs, electrical works, fire tanks and fire pumps, and a pump station.
Due to the urgency of the commencement of the Raw Water Pipeline, our manufacturing team fabricated various large diameter air and scour tees as well as various isolation valve assemblies in our own Fabrication Workshop.
![]() |
![]() |












